Just when things were going so well, and despite us having done our best to make sure we had all the permissions for everything sorted out, our project had to be put on hold while we addressed a number of issues raised by the Ayuntamiento.

Unfortunately this led to a delay of 4 months on the project. What’s worse, during this period when nobody was on site, it was broken into and around 3,000€ of materials were stolen.

Fortunately everything was sorted out in the end and we’re now looking forward to getting on with the project. Onward and upward…