4 December 2022 Progress is shifting more towards the inside now. All the admin areas now have a roof. Dividing…
New Year, New Kennels
8 January 2023 So 2023 has arrived and this is the year that we will be moving in to the…
Construction almost done!
24 September 2023 You can see from today’s update that the main construction of the Phase 2A kennels is almost…
Phase 1 complete, now phase 2 begins to take shape
4 June 2023 Phase 1 is there apart from the electricity supply (we hope to have an exciting update about…
New Build Contract Signed
5 April 2022 Today is a historic day for SAT. Today the build contract for the first phase of the…
Progress on the shell
29 May 2022 Progress continues on the exterior shell of the building. The walls of the office, staff and vet…